Cheat-sheet hub

Process groups, formulas, agile ceremonies, EVM — all on one page.

Process Groups & Knowledge Areas

Process
Initiating
Develop charter · Identify stakeholders
Planning
Scope, schedule, cost, quality, resource, comm, risk, procurement, stakeholder mgmt plans
Executing
Direct & manage work · Manage quality · Acquire/develop/manage team · Conduct procurements
Monitoring & Controlling
Validate scope · Control schedule/cost/quality/risks · Perform integrated change control
Closing
Close project or phase · Final lessons learned

EVM Formulas

Formulas
PV (Planned Value)
Budgeted cost of work scheduled
EV (Earned Value)
% complete × BAC
AC (Actual Cost)
Money actually spent
CV / SV
CV = EV − AC · SV = EV − PV
CPI / SPI
CPI = EV / AC · SPI = EV / PV
EAC (typical)
EAC = BAC / CPI
EAC (atypical)
EAC = AC + (BAC − EV)
ETC
ETC = EAC − AC
VAC
VAC = BAC − EAC
TCPI
(BAC − EV) / (BAC − AC)

Abbreviation key

PVPlanned Value
EVEarned Value
ACActual Cost
BACBudget at Completion
CVCost Variance
SVSchedule Variance
CPICost Performance Index
SPISchedule Performance Index
EACEstimate at Completion
ETCEstimate to Complete
VACVariance at Completion
TCPITo-Complete Performance Index

Scheduling & PERT

Formulas
PERT (Beta)
(O + 4M + P) / 6
Triangular
(O + M + P) / 3
Std deviation
(P − O) / 6
Variance
((P − O) / 6)²
Float / Slack
LS − ES = LF − EF
Critical path
Longest path · zero total float
Comm channels
n(n − 1) / 2

Abbreviation key

PERTProgram Evaluation and Review Technique
OOptimistic estimate
MMost likely estimate
PPessimistic estimate
ESEarly Start
EFEarly Finish
LSLate Start
LFLate Finish
nNumber of stakeholders / team members

Agile / Scrum Ceremonies

Agile
Sprint Planning
Set sprint goal & backlog · ≤ 8h for 1-month sprint
Daily Scrum
15 min · team-only · plan next 24h
Sprint Review
Inspect increment with stakeholders · ≤ 4h
Retrospective
Inspect process · ≤ 3h · improvement actions
Backlog Refinement
Ongoing · clarify, estimate, split stories
Roles
Product Owner · Scrum Master · Developers
Artifacts
Product Backlog · Sprint Backlog · Increment

Risk Responses

Process
Threats
Avoid · Transfer · Mitigate · Accept · Escalate
Opportunities
Exploit · Share · Enhance · Accept · Escalate
EMV
Probability × Impact (sum across outcomes)
Reserves
Contingency = known-unknowns · Management = unknown-unknowns

PMI Mindset (test heuristics)

Mindset
Always
Plan first · Prevent over inspect · Talk to people directly
Servant leader
Remove impediments · Coach, don't command
Change
Never skip integrated change control
Conflict
Collaborate / problem-solve first
Issues
Address at lowest level · escalate only when blocked
Hybrid
Tailor — pick what fits the context, not dogma

Bring it to exam day

Use the brain-dump template to offload formulas in your first 2 minutes.